This page will be updated 3 to 4 times a day to communicate progress of snow clearing operations during a winter event.

This activity report is for a Winter event starting on November 16, 2022

Report Updated: November 16, 2022 @ 8:15 am

End of snow clearing operations: 1:30 pm

Activity Report

Forecasted Snow Accumulation

Actual Snow Accumulation

North of Taunton: 3-7 cm
South of Taunton: 3-7 cm

North of Taunton Road: 4-5 cm
South of Taunton Road: 4-5 cm

Areas of Service - Roads

Comments

Main (Arterial/Collector) Roads

Liquid Salt Brine: N/R
Salted: Completed
Plowed: N/R

Start time: 2:00 am 
Estimated completion time: 4:00 am
Completion time: 4:00 am

Residential (Local) Roads

Liquid Salt Brine: N/R
Salted: Completed
Plowed: N/R

Start time: 4:00 am 
Estimated completion time: 7:00 am
Completion time: 7:00 am

Gravel Roads
Plowed: Completed
Sanded: Completed

Start time: 8:00 am
Estimated completion time: 3:00 pm
Completion time: 1:30 pm 

 

Area of Service - Sidewalks

 

Main Sidewalks

Salted: Completed

Plowing: Completed

Secondary Sidewalks 

Salted: Completed
Plowing: Completed


Start time: 4:30 am

Estimated completion time: 2:00 pm

Completion time: 1:30 pm

 

Area of Service - Seniors & Persons with Disabilities Snow Clearing Program

 

Due to the minimum 5 cm of snow accumulation not being reached, the Senior Snow Clearing Program will not be initiated.

Start time: TBD
Estimated completion time: TBD
Completion time: TBD