This page will be updated 3 to 4 times a day to communicate progress of snow clearing operations during a winter event.

This activity report is for a Winter event starting on March 19, 2023

Report Updated: March 19, 2023 @ 6:00 am

End of snow clearing operations: TBD

Activity Report

Forecasted Snow Accumulation

Actual Snow Accumulation

North of Taunton: Trace - 1
South of Taunton: Trace -1 cm

North of Taunton Road: 1 cm
South of Taunton Road: 1 cm

Areas of Service - Roads

Comments

Main (Arterial/Collector) Roads

Liquid Salt Brine: TBD
Salted: Salting in progress
Plowed: TBD

Start time: 6:00 am
Estimated completion time: 9:00 am
Completion time: TBD

Residential (Local) Roads

Liquid Salt Brine: TBD
Salted: Salting in progress
Plowed: TBD

Start time: 6:00 am 
Estimated completion time: 11:00 am
Completion time: TBD

Gravel Roads
Plowed: TBD
Sanded: TBD

Start time: TBD
Estimated completion time: TBD
Completion time: TBD

Area of Service - Sidewalks

 

Main Sidewalks

Salted: TBD
Plowing: TBD

Start time: TBD 
Estimated completion time: TBD

Completion time: TBD

Secondary Sidewalks

Salted: TBD
Plowing: TBD

Start time: TBD

Estimated completion time: TBD

Completion time: TBD

Area of Service - Seniors & Persons with Disabilities Snow Clearing Program

 

Minimum requirement not met will not be dispatched

Start time: TBD
Estimated completion time: TBD
Completion time: TBD